page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68 page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
66 CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
4.7 Construction of canals
4.7.1 DESCRIPTION
Once the canal type has been selected and the design carried
out, there are four stages in the actual construction as follows;
setting out of the course of the canal,
preparing the bench for the canal,
excavating the canal, and
lining the canal.
These sections describe a general method of canal
construction and offer examples of other proven methods that
may be suitable under certain conditions.
4.7.2 SETTING OUT
Setting out the canal requires the following equipment and
staff:
Basic equipment:
Level machine (or Dumpy level)
Measuring tape
Tripod
Wooden pegs
Machetes
Mallet
Pick
Hoe
Paint
Paintbrush
Staff:
Surveyor
Chainperson (assistant to surveyor)
Helper to clear vegetation and prepare pegs
The setting out of the canal is done by placing pegs along the
alignment. Depending on the topography, such pegs should
generally be placed at 5 to 20 m intervals along the alignment.
Pegs should also be placed at bends, structures such as drops.
and the beginning and end of crossings and superpassages.
Some intermediate pegs or reference pegs should be placed
just outside the canal alignment using a level machine (or a
Dumpy level). With the use of the level machine, the
difference in levels between these pegs can be calculated.
Such pegs will serve as reference levels for the excavation
work. An alternative to this is to paint marks at exposed rocks
just outside the alignment and calculate their levels.
4.7.3 BENCH CUT
The bench of a canal is like a road of uniform width and slope,
see Figure 4.12. The bench is prepared by excavating a strip
of land of even width along the pegs placed earlier on the
canal alignment.
The bench width should be the top width of the canal plus an
allowance for berms on each side of the canal. On the hill
side, a berm of 300 mm is recommended, so that material
washed down by rain from the slope above is not deposited
directly in the canal. A 1.0 m wide berm is recommended on
the outside of the bench, to reduce seepage through the canal
bank, and to provide access for construction and maintenance.
A lesser berm should only be used in conjunction with vertical
cement masonry walls founded on rock. Note that a berm
width less than 500 mm is difficult to walk along.
The slope of the bench should be the same as the slope (S) of
the canal section. Therefore, where there is a change in the
canal slope (in the design) the bench slope should also change
accordingly. The levels of the canal and the bench at different
locations can be verified using a theodolite or a level machine
and the intermediate pegs that were placed outside the canal
alignment earlier.
Once the initial level at the intake is fixed, the subsequent
levels can be calculated based on the slopes. The initial level
can be estimated based on the contour maps of the area or by
an altimeter. Another method is to use the trigonometric
points established by the survey department, but this may
take longer and require more resources. The initial level does
not have to be very accurate (i.e. the exact elevation from the
sea level) but the differences between intermediate pegs
should be accurate, since it is these differences that determine
the slope of the canal.
An example of a level calculation is presented below:
The designer has recommended a slope of 1.5% for a certain
canal section. The topographic map of the area indicates that
the elevation at the intake is around 1600 m above mean sea
level (MSL).
In this case the first peg that is placed at the intake area can
be assumed to be at a level of 1600 m above MSL. If the
second peg is to be placed 20 m (horizontal length)
downstream, the bench level here should be: 20 m x 1.5/100
= 0.30 m down from the intake or 1600 m - 0.30 m
= 1599.70 m above MSL
The subsequent readings between intermediate pegs (i.e.
reference points) can be noted in sequence with similar
calculations.
Figure 4.12 Canal bench